Supply Co Residents Update

We continue to see significant progress on the site with the relocation of the storm water drain and all piling works now complete. The construction team have encountered some rock whilst digging the basement but despite this have been making good progress.

Considerable change will be seen at the site in coming months with the focus being on:

  • The bulk excavation to the basement which is expected to be finished by 30 June. Additional resources have been committed by the builder to ensure this is completed on schedule;
  • Completing the construction of the capping beam and commencing the formation of the shotcrete walls, both of which form important structural components of the completed building;
  • Continuing the sales campaign for the remaining apartments, of which only 17 remain available. The majority of interested buyers continue to be owner occupiers.